Question:
Will a proposal cover and table of contents page be
included as part of the 15 pages?
Answer:
No
Page 8 of 10, Section III Miscellaneous, #1:
Describe your general
conditions including a not to exceed % or amount.
Change - Page 2 of 10, paragraph I, subparagraph B, last bullet:
Contributions: Actively, and in conjunction with the
Fresno Chaffee
Zoo, pursue, offer, secure and/or incorporate ideas, partnerships,
and donations of materials or funds from appropriate donors or vendors
during the design and construction process.
Page 7 of RFQ
A. EXPERIENCE AND QUALIFICATIONS OF THE FIRM/TEAM
1. Identify at least three (3) projects, especially related to a
zoological or aquatic facility, in which the firm served as either
CM@Risk, Agency CM and/or General Contractor. For each project please
provide the following:
Question:
Is zoological project experience required?
Answer:
Zoological experience is helpful but not required; other
experience that will be considered is related to construction manager
at risk, similar sized projects, projects of this complexity and uniqueness,
aquatic projects, animal facilities, and other related experience.